Construction update

September 2021
construction update

Construction is progressing well at Liberty One with the building core now reaching Level 19, and the first concrete pour on Level 15 underway. Additionally, Level 15 formwork has completed and Level 10 is now fully framed

Further milestones include the completion of the window installation on Level 11 and the commencement of joinery installation across Levels 2 and 3.

​​​​​​​Subject to council approvals, the anticipated completion
​​​​​​​date of Liberty One apartments is July 2022.